top of page

SECURITY FORCES MEDICAL CITY (SFMC)

Jeddah, KSA

The Security Forces Medical City is one of the largest medical investments in the GCC. The total area of the city is almost 2.5 million m2 of which the hospital is nearly 500.000 m2.

​

Airdeck was selected as the lightweight floor system for the hospital building. Flexibility in the project was very important and Airdeck came up with a tailor made drilling protocol to allow future drillings in the hospital building structure.

​

The project is currently under construction and over 350.000 m2 of Airdeck panels will be delivered.

parties involved sfmc.png

Images of the project

More information?

Feel free to contact us

SFMC 1

Lower reinforcement (including lattice girders) for the Airdeck elements is prepared in the factory

SFMC 2

The slab of 7cm is poured in the factory in Riyadh

SFMC 3

Airboxes are correctly positioned in the freshly poured concrete

SFMC 4

Curing process of the Airdeck elements

SFMC 5

Ready for transport. The elements can be stacked on top of each other.

SFMC 6

Special frames underneath the stack of plates make sure a safe transport can be done

SFMC 7

The lifting points are indicated for the contractor

SFMC 8

Special crosses are installed between the planks to make sure no cracks can occur

SFMC 9

Lifting at the construction site in Jeddah

SFMC 10

Unloading can be done by only a few workers.

SFMC 11

A stock can be build at the construction site if desired

SFMC 12

Each element has a unique identification number

SFMC 13

Lifting of the elements with a 8-points lifting system

SFMC 14

Installation of the elements on temporary supports

SFMC 15

Fast and secure installation

SFMC 16

Once the elements are installed, the upper reinforcement works can start

SFMC 17

The elements (and even the Airboxes) are safe to walk on

SFMC 18

Upper reinforcement is ready. The floor can be poured with concrete.

SFMC 19

Concrete pouring. Less concrete is needed because of the airboxes (void formers).

SFMC 20

Aerial view: different stages of construction can be combined

SFMC 21

Aerial view: upper reinforcement can be installed on the elements on top

SFMC 23

Aerial view: different stages are visible (preparation of temporary supports, upper reinforcements, finished areas, ...)

SFMC 23

Aerial view: floors are ready to be poured with concrete

SFMC 24

Aerial view: concrete works in progress

SFMC 25

Bottom view: temporary supports

SFMC 26

Bottom view: temporary supports are being removed

SFMC 27

Bottom view: the floor is finished

SFMC 28

Bottom view: the floor is finished

bottom of page